• Project

SR 305/Sam Snyder Creek – Remove Fish Barrier

Project overview

This project will remove two existing 270-foot-long, 36-inch-diameter concrete pipe culverts on State Route 305 outside of Poulsbo at the Sam Snyder Creek crossing and replace them with a single 239-foot-long steel girder bridge. General work activities include: clearing and grubbing, earthwork structure installation, paving, stream profile realignment and streambed restoration.

Timeline
October 2023 - Spring 2025
Project status
Construction
Funding
$36.4 million

What to expect

Work is wrapping up on the new bridge over Sam Snyder Creek. In early May, permanent markings will be put down on the roadway. Once that is complete, both directions of the new bridge will be open to traffic.

A fish barrier underneath State Route 305 outside of Poulsbo will be replaced with a new bridge.